The Report proposes an approach of guaranteeing permitting timelines and the development process improvements to support the proposed timelines. Outlined below are the proposed processing targets.
Permit Types | Current Target | Proposed Guaranteed Timeline |
Rezoning Report to Council (Single Family (w/o DP) | None established | 12 weeks |
Rezoning Report to Council - Multifamily, Commercial & Industrial (w/ DP) | None established | 16 weeks* |
Building Permit - Single Family | 10 weeks | 10 weeks |
Building Permit - Tenant Improvement | 10 weeks | 10 weeks |
* An additional 3-4 weeks processing time required for projects requiring ADP review