2021/10 # Surrey # New Development Approval Timeline #素里市推出土地审批时间表

作家相片: ERIC WANGERIC WANG

The Report proposes an approach of guaranteeing permitting timelines and the development process improvements to support the proposed timelines. Outlined below are the proposed processing targets.

Permit Types

Current Target

Proposed Guaranteed Timeline

Rezoning Report to Council (Single Family (w/o DP)

None established

​12 weeks

Rezoning Report to Council - Multifamily, Commercial & Industrial (w/ DP)

None established

16 weeks*

Building Permit - Single Family

10 weeks

10 weeks

Building Permit - Tenant Improvement

10 weeks

10 weeks

* An additional 3-4 weeks processing time required for projects requiring ADP review